Screen Shot 2017-01-27 at 11.41.29 AMPhase II is a 100 X 130 butler building that will have a gym (fellowship hall), kitchen, children’s wing, and nursery wing.  It will have a second floor above the nursery wing.

We are going into this project with the idea that the second floor will not be completed until a much later date. Screen Shot 2017-01-27 at 11.28.33 AM

Our current gym will be transformed into 5 new Sunday school rooms, new office space, and and expanded worship department room.  On Sunday mornings, we are currently occupying every classroom that is available, including the fellowship hall.

We have been averaging between 150-200 in Sunday school for quite sometime now.  Simply put, we have no where to expand.  For us to continue to grown, we must stay committed to discipleship.

The way we disciple new believers is through small group Sunday school.  Our banquets and outreaches have also outgrown our current gym.

The missions banquet, Valentines banquet, church meals, etc, have all grown to the point that we have to put limits on the number of attendees, which is something we would prefer to avoid.

The upstairs of our current gym will include a new youth room but will be completed at a later date.

Follow along with our progress by following us on FaceBook!

To make a pledge towards Phase II, please click here!

                                                                                                                                   Screen Shot 2017-01-27 at 11.27.26 AM

On July 15th, 2018, our church membership has voted unanimously to move forward with the building of our new 13,000 square foot Family Life Center.  This building will provide a new children’s church room and a larger nursery for our kids in addition to a new gymnasium, kitchen, and classrooms. After the completion of the new Family Life Center, we will also remodel our old gym into Sunday school classrooms, office space, and a youth worship room.  We at the Revival Center are excited for what God is doing in our midst.  We are hoping and praying to break ground late 2018/early 2019.  We will keep everyone updated with any new details that arise.

Capital Building Campaign will last 36 months from April 9, 2017 to April 2020

Goal to start building: January 2019 (Takes 6 months to build.)